1、本標(biāo)段采用排水固結(jié)施工的路段約2.25km,排水板采用C型,截面尺寸100×4.5mm,間距1.0~1.6m,梅花形布置,要求打穿軟土進(jìn)入砂層0.5m以上,當(dāng)軟土層超過24.5m時,排水板深度按25m控制,具樁號劃分及布置見附圖。
2、場地清理完成后,對于一般路段,首先攤鋪水平排水砂墊層,接著進(jìn)行塑料插板施工,而后進(jìn)行路基施工;對于遇水塘路段,首先砌筑攔水圍堰,吹填砂至常水位以上50cm,然后攤鋪水平排水砂墊層,進(jìn)行塑料插板施工。
3、塑料排水板采用套筒式施工,插設(shè)完成后的排水板伸出排水墊層20cm.,塑料排水板需要接長時,必須采用濾膜內(nèi)芯板平搭接的方式,搭接長度不得小于200mm。嚴(yán)格控制回帶長度,不得超過500mm,否則要在附近補(bǔ)打,回帶的根數(shù)應(yīng)控制在總打設(shè)根據(jù)數(shù)5%以內(nèi)。
4、塑料排水板在插入地基的過程中應(yīng)保證排水板不扭曲,透水膜不被撕破和污染。并且排水板底應(yīng)有可靠的錨固措施,以免在抽出保護(hù)套管時,將其帶出。
5、塑料排水板插入好后應(yīng)及時將露出砂墊層的部分切斷,并將它保護(hù)好,以防因打樁機(jī)移動、車輛的進(jìn)出或者下雨損壞而降低排水效果。
6、施工前塑料排水板應(yīng)堆放在現(xiàn)場并加以適當(dāng)?shù)牡母采w以防暴露
Cards on the table contents:
1, the construction of the tenders section of consolidation with drainage of about 2.25km, drain board with C-type, section size 100 × 4.5mm, pitch 1.0 ~ 1.6m, plum-shaped layout, penetrated the soft soil into the sand required more than 0.5m When the soft soil over 24.5m, the drain depth control by 25m, with Stake division and layout, see photos.
2, site clean-up is completed, the general sections, the first level of the drainage paving sand cushion, followed by plastic boards in construction, then for roadbed construction; for the case of reservoir sections, the first masonry to hold water cofferdam, fill sand to constant level over 50cm, and then paving the level of drainage sand cushion, plastic boards for construction.
3, plastic drainage plate with sleeve-type construction, inserted after the completion of the drainage board set out the drainage blanket of 20cm., Plastic drain to pick up a long time, must be used within the core board flat membrane overlapping manner, Lap length not less than 200mm. Strictly control the back with a length of not more than 500mm, or up to fight in the vicinity, back to the root of the number should be controlled with the total number of Installation under 5%.
4, plastic drain board in the insertion process should ensure that the foundation drains are not distorted, permeable membrane is not torn and pollution. And the drain end of the anchorage should be reliable measures to avoid when taking the protection sleeve, brought out.
5, plastic drain into good will come out in time after cutting off part of the sand cushion and protect it to prevent movement due to pile-drivers, vehicle access or rain damage and reduce the drainage effect.
6, before construction of plastic drain board must be put in the scene and make the appropriate coverage to prevent exposure