水泥土攪拌樁技術(shù)交底
水泥土攪拌樁在橋臺(tái)臺(tái)后60米范圍內(nèi)采用。樁徑55сm樁間距1.2~1.8米,梅花形布置,樁應(yīng)穿過淤泥層0.5米當(dāng)淤泥層厚度大于16米時(shí),樁長(zhǎng)按16米控制。
一、材料:
水泥采用普通硅酸鹽水泥,強(qiáng)度32..5必須有出廠合格證和化驗(yàn)單,并按規(guī)范實(shí)驗(yàn)。水采用自來水或經(jīng)化驗(yàn)合格的河水。
二、施工工藝
1、 場(chǎng)地準(zhǔn)備。清除地表雜土、腐植土、壓實(shí)。
2、 測(cè)量定位。按設(shè)計(jì)要求的間距測(cè)放樁位。如要變更設(shè)計(jì)樁位,需經(jīng)設(shè)計(jì)、監(jiān)理同意。
3、 試樁
先按不同的地質(zhì)段進(jìn)行試樁,以掌握現(xiàn)場(chǎng)的成樁參數(shù),拒此指導(dǎo)施工,試樁數(shù)不少于5根
4、 根據(jù)各段設(shè)計(jì)樁長(zhǎng),對(duì)鉆桿用油漆做好標(biāo)記,以便掌握鉆進(jìn)的深度。
5、 樁機(jī)定位對(duì)中,調(diào)正導(dǎo)軌的垂直度。
6、 預(yù)拌下沉到設(shè)計(jì)深度。
7、 提升噴漿攪拌。開啟灰漿泵將水泥漿壓入路基土中,邊噴漿邊旋轉(zhuǎn),邊按試樁確定的提升速度提升攪拌機(jī),停漿面比設(shè)計(jì)樁頂標(biāo)高高出50сm。
8、 重復(fù)上、下攪拌,共四拌兩噴。
9、 清洗。向集料斗中注適量的清水,開啟灰漿泵,將管路中殘存的水泥漿清洗干凈,清除攪拌頭上的土。
DJMP Technology Details <br> <br>Cement mixing pile in the bridge abutment used within 60 meters. 55сm pile pile diameter spacing 1.2 and 1.8 meters, plum-shaped arrangement, the pile should be through the mud when the mud layer thickness of 0.5 m greater than 16 meters, 16 meters length of pile under control. <br> 1, material: <br> Cement with ordinary Portland cement, strength of 32 .. 5 certificate must have a factory and laboratory test, in accordance with standard test. Water with tap water or water tests qualified. <br> Second, construction technology <br>1, site preparation. Clear the surface mixed soil, humus, compaction. <br>2, measuring orientation. According to the design of distance measurement up Pile. To change the design of pile position, subject to the design, supervision and consent. <br>3, test pile <br>Press the different geological sections test pile to pile parameters control the scene, refused this guide the construction, test piles not less than five <br>4, according to the design section of pile length on the drill pipe and marked with paint in order to grasp the depth of drilling. <br>5, pile driver positioning, the tone is guide rail perpendicularity. <br>6, ready-mixed sink to the design depth. <br>7, to enhance spray mixing. Open the ash slurry pump will be pressed into the soil subgrade, side spray side rotation, edge enhancement by test pile to determine the speed upgrade mixer, stop slurry surface elevation higher than the design pile top 50сm. <br>8, to repeat, on stirring, a total of four two-jet mixing. <br>9, wash. Hopper in the note to set the right amount of water, open the ash slurry pump, the remaining slurry pipeline in the clean, clear mixing head of the soil. <br>