深層攪拌樁施工技術交底記錄.doc
進入下載頁
交底內(nèi)容:
1. 本處理地段攪拌樁樁徑Ф600mm(攪拌鉆頭不小于Ф600mm),設計樁長不等,樁底進入土體持力層0.5~1m,單樁承載力不少于120KN;施工時,樁底高程不高于設計標高,樁頂高程不低于設計標高;行車道樁距為1.2×1.2m,按等邊三角形梅花型排列,經(jīng)處理后的復合地基承載力120Kpa;人行道樁距為1.5×1.5 m,按等邊三角形梅花型排列。
2. 制漿采用32.5R普通硅酸鹽水泥,漿液水灰比為0.4~0.5。為增加攪拌樁的早期強度,按水泥用量的0.05%添加三乙醇胺。制備好的漿液不得離析,泵送必須連續(xù)。每加固1m土體摻入水泥量為70kg,單樁水泥用量偏差不大于5%。
3. 攪拌頭上提噴漿時的提升速度為0.5~0.8m/min,噴漿壓力為0.4~0.6MPa。
4. 測放樁位按設計要求進行,在確定孔位時,需經(jīng)復核確認后方可進入下一施工工序,為保證樁位的準確性,樁位必須打入木樁或插入竹片作為樁位標記。
5. 下鉆桿時,先使樁機安置在標定的孔位上,使鉆頭中心對準孔中心,桿位偏差在±5cm以內(nèi),調(diào)整樁機水平度及垂直度,保證孔斜率不大于1.0%,終孔后校正鉆具,樁徑偏差不得大于4%。
6. 下鉆桿攪拌前要通過地面試噴清水,檢查灌漿設備和管路系統(tǒng)、設備的壓力和排量必須滿足設計要求;管路系統(tǒng)的密封圈必須良好,各通道和噴嘴內(nèi)不得有雜物。
7. 根據(jù)施工設計控制攪拌技術參數(shù),注意漿液流量,自上而下攪拌,自下而上噴漿攪拌。當土層較硬時,可適當提高水泥漿水灰比。
8. 施工人員必須認真檢查水泥漿的水灰比和流量,灌漿泵壓力和攪拌桿的提升速度,回轉(zhuǎn)速度等施工參數(shù)是否符合要求,并及時作好施工現(xiàn)場記錄。另在攪拌過程中,應控制鉆桿的進入深度。
9. 單樁開鉆后應連續(xù)施工,嚴格控制起噴和停噴高程,不得間斷。如遇停機或機械故障停噴,應及時記錄中斷高程,待恢復正常后立即復攪,復攪重疊長度不小于1m。如中斷時間超過12小時,應采取補樁措施。
(轉(zhuǎn)下頁)
Cards on the table contents:
1. The processing site mixing pile diameter Ф600mm (mixing drill not less than Ф600mm), design of pile length ranging from the bottom into the soil pile bearing stratum 0.5 ~ 1m, bearing capacity of not less than 120KN; construction, pile bottom elevation is not higher than the design elevation, the pile top elevation of not less than the design elevation; lane pile spacing is 1.2 × 1.2m, according to an equilateral triangle plum-type arrangement, the treated composite foundation 120Kpa; sidewalk pile spacing of 1.5 × 1.5 m, according to an equilateral triangle plum-type arrangement.
2. Pulping using 32.5R ordinary portland cement, slurry water cement ratio of 0.4 to 0.5. To increase the mixing of the early strength, cement content of 0.05% by adding triethanolamine. No segregation of prepared slurry, pumping must be continuous. Strengthening 1m per volume of soil mixed with cement 70kg, single pile of cement consumption is not more than 5% deviation.
3. Mixing spray head to mention the improvement when the rate of 0.5 ~ 0.8m/min, spray pressure 0.4 ~ 0.6MPa.
4. Measurement Pile up by design requirements, in determining the hole, the need to be confirmed by the review into the next construction process, in order to ensure the accuracy of the Pile, Pile must be inserted into the stakes or bamboo as the pile bit tag.
5. Under the drill, the first to pile driver placed in the calibration of the holes, so that the drill center hole aligned center pole position deviation within ± 5cm to adjust the level of degree and verticality of pile driver, to ensure the slope is not greater than hole 1.0%, after the correction of the final hole drilling, pile diameter deviation of not more than 4%.
6. Stirring before the next drill pipe to the interview by spraying water, check the grouting equipment and piping systems, equipment, pressure and displacement to meet the design requirements; piping system must have good seal, the channel and nozzle may have mixed material.
7. Under the control of construction and design parameters of mixing technology, attention to slurry flow, mixing top-down, bottom-up spray mixing. When the soil harder, the water cement ratio cement slurry can be raised properly.
8. The construction personnel must carefully inspect the water-cement ratio and the flow of slurry, pressure grouting pump and stirring rod to enhance the speed, rotation speed of the construction parameters of compliance requirements and make timely record of the construction site. The other in the mixing process, should control the entry of the depth of the drill pipe.
9. After drilling pile construction should be continuous, strictly control the elevation from the jet and Minting without interruption. In case of downtime or a mechanical failure Minting, shall promptly record interrupt elevation, to be back to normal immediately after the resumption of stirring, complex mix overlap length of not less than 1m. If interrupted for more than 12 hours, measures should be taken to pile up.
(Next page)