排水工程土方回填施工技術(shù)交底記錄.doc
進(jìn)入下載頁
交底內(nèi)容:
1、在用攪拌樁進(jìn)行復(fù)合地基處理的區(qū)域,回填前應(yīng)挖除攪拌樁樁頂浮土,回填30cm厚砂礫材料,并碾壓密實(shí)。
2、填方材料使用現(xiàn)場內(nèi)開挖的材料,并保證其在規(guī)定的含水量狀態(tài)下能被壓實(shí)到設(shè)計(jì)規(guī)定的密實(shí)度。
3、填筑前要對路基、臺背等進(jìn)行基底清理,保證施工場地能按設(shè)計(jì)要求進(jìn)行平整壓實(shí)。
4、填土路基必須根據(jù)設(shè)計(jì)斷面分層填筑壓實(shí),其分層填筑厚度必須與壓實(shí)機(jī)具相適應(yīng),一般每層松土填土厚度不應(yīng)超過30cm。路基填筑壓實(shí)寬度不得小于設(shè)計(jì)寬度,以便最后削坡,嚴(yán)禁貼坡。
5、每一壓實(shí)層均應(yīng)檢驗(yàn)壓實(shí)度,合格后方可填筑上一層。否則應(yīng)查明原因,采取措施進(jìn)行補(bǔ)壓。檢驗(yàn)頻率每2000m²檢驗(yàn)8點(diǎn),不足2000m²時(shí),至少應(yīng)檢驗(yàn)兩點(diǎn),必須每點(diǎn)都符合施工規(guī)范(JTJ071--98)及設(shè)計(jì)要求。必要時(shí)可根據(jù)需要增加檢驗(yàn)點(diǎn)。試驗(yàn)報(bào)告要注明土料種類、試驗(yàn)日期、試驗(yàn)結(jié)論及試驗(yàn)人員簽字。未達(dá)到設(shè)計(jì)要求的部位應(yīng)有處理方法和復(fù)驗(yàn)結(jié)果。
6、路基修筑前15天應(yīng)在取土地點(diǎn)取樣進(jìn)行擊實(shí)試驗(yàn),確定其最佳含水量和最大干密度。碾壓前應(yīng)先測定土的實(shí)際含水量是否符合或接近最佳含水量。如果回填土太干燥,應(yīng)在碾壓前對干土適當(dāng)灑水加以潤濕;如回填土太濕,壓不密實(shí)呈“橡皮土”現(xiàn)象,這時(shí)應(yīng)將“橡皮土”挖出,重新?lián)Q土再碾壓。
7、回填作業(yè)時(shí),先填低洼路段,后填一般路段;先填路中,再逐漸填到路邊。按水平分層逐層填筑,分層碾壓,每層壓實(shí)度要達(dá)到90%以上。不得順坡鋪填,最大層厚不超過20cm,土塊粒徑≤10cm。
8、碾壓機(jī)行走方向應(yīng)平行路基中線,相鄰作業(yè)面的搭接碾壓寬度,平行路中線方向不應(yīng)小于50cm,機(jī)械碾壓不到的部位,應(yīng)輔以夯實(shí),夯實(shí)時(shí)應(yīng)采用連環(huán)套打法,夯跡雙向套壓,夯跡搭壓寬度不小于1/3夯位。
9、碾壓時(shí),應(yīng)遵循先輕后重、先穩(wěn)后振、先慢后快、先邊后中、先高后低以及輪跡要疊的原則。
(轉(zhuǎn)下頁)
Cards on the table contents:
1, with mixing pile composite foundation of the region, mixing pile excavation before backfilling the top surface dust, gravel backfill material 30cm thick and compacted dense.
2, use of materials on-site fill material within the excavation and to ensure its state water content in the prescribed design requirements can be compacted to the density.
3, before filling of the foundation, basement, etc. Back of clean-up, to ensure construction site can be formed according to design requirements compaction.
4, the design section must fill embankment dam compaction layer, the thickness of the layer filling and compaction equipment to be adapted, generally should not exceed the thickness of each layer loose soil fill 30cm. Roadbed construction shall not be less than the design width of the width of compaction to the final cut slopes, slope paste strictly prohibited.
5, each compacted layer shall be test compaction, pass on the floor only after filling. Otherwise, to identify causes and take measures to fill pressure. Inspection frequency for each test 8:00 2000m ², less than 2000m ², at least two points should be examined, must conform to construction specifications for each point (JTJ071 - 98) and design requirements. Can be increased if necessary checkpoint. Soil test report should indicate the material type, test date, test findings and the signature test. The site does not meet the design requirements should be handling and retest results.
6, 15 days before the embankment construction sites should take soil samples for compaction tests to determine the optimum water content and maximum dry density. RCC preceded the actual determination of soil water content is consistent with or close to the optimum moisture content. If the backfill is too dry, should be properly compacted soil dry before watering to wet; as backfill is too wet, compaction pressure was not "rubber soil" phenomenon, when the words "rubber soil" dug out, re-for-land re-rolling.
7, filling operations, filling low-lying sections of the general section after filling; filling path, and then gradually fill in the street. Stratified by the level of layer filling, layered, rolled, each layer compaction to more than 90%. Not downslope the filling, the maximum thickness of no more than 20cm, clods size ≤ 10cm.
8, rollers should be parallel to the embankment center line direction of travel of the adjacent working surface of the lap rolling width, parallel to the road center line direction of not less than 50cm, mechanical rolling less than the parts, should be complemented by compaction, compaction should be used comic play set, two-way set of track tamping pressure, take the pressure of tamping track width not less than 1 / 3 ram position.
9, RCC should be followed after the first light weight, after the first steady vibration, the first slow after the fast, the first edges, the first high to low and the wheel track to stack principle.