1、 必須按施工組織設(shè)計(jì)進(jìn)行施工。
2、 搭設(shè)、拆除腳手架必須戴安全帽及穿軟底鞋。
3、 外墻腳手架必須在主體結(jié)構(gòu)施工以前搭設(shè),并按照有關(guān)規(guī)定搭設(shè)安全檔板或者安全網(wǎng);腳手架應(yīng)高出工作面1.2M以上。
4、 用于連接大橫桿的對(duì)接扣件,應(yīng)避免開口向上設(shè)置,防止雨水侵入。
5、 腳手架分段或搭設(shè)完畢,須經(jīng)施工負(fù)責(zé)人、質(zhì)安員驗(yàn)收合格后,方可使用;高層建筑的外墻腳手架要采取卸荷措施。
6、 在大風(fēng)雨或停工一段時(shí)間后、應(yīng)對(duì)腳手架進(jìn)行全面檢查,如發(fā)現(xiàn)變形、下沉、鋼構(gòu)件銹蝕嚴(yán)重,連接扣松脫等,要及時(shí)加固維修后方可使用。
7、 拆除腳手架應(yīng)設(shè)圍欄,拆除工作應(yīng)由上而下,一步一清,不準(zhǔn)上下同時(shí)作業(yè),拆除物件不得往下投擲。
8、 拆除大橫桿、剪刀撐時(shí)應(yīng)先拆中間扣,再拆兩頭扣,由中間操作人員往下順傳竹桿。
9、 遇大雨、雷、五級(jí)以上及夜間不得作業(yè)。
用Φ6鋼筋預(yù)埋砼梁外邊,每3米水平設(shè)一道,待砼梁板拆除后,收緊鋼筋,再加回頭頂。
Security cards on the table contents:
1, must be constructed according to the construction organization design.
2, erection, dismantling scaffolds must wear a helmet and wear soft-soled shoes.
3, external scaffolding prior to erection of the main structure of the construction and erection of security in accordance with relevant provisions of the tailgate or the safety net; scaffold should be higher than face 1.2M.
4, a large bar for connecting the docking fasteners, should be set up to avoid openings to prevent water intrusion.
5, section or scaffolding erection is completed, subject to construction of person in charge of quality inspection and acceptance by security guards only after use; high-rise building external scaffolding unloading measures to be taken.
6, when the storm or after a period of suspension of work, scaffolding should conduct a comprehensive inspection, if found deformation, subsidence, severe corrosion of steel components, connecting buckle loose, they have to be repaired in time to use reinforcement.
7, removal of the fence should be set up scaffolding, demolition work should be top-down, step one clear, closed down operations at the same time, removal of objects not throw down.
8, removal of a large bar, scissors should be removed first, middle button, and then split two buttons, the operator by the middle pass down the smooth bamboo.
9, heavy rains, thunder, and night shall not work more than five.
Reinforced concrete beam embedded with Φ6 outside, set a level of 3 meters each, to be removed after the concrete slab, to tighten the steel, coupled back to top of the head.