廣州南沙開發(fā)區(qū)黃閣東二路道路工程路基填筑技術(shù)交底.doc
進入下載頁
交底內(nèi)容:
本工程的路基填筑在軟基處理完成后先攤鋪30cm厚碎石墊層,再鋪一層40型雙向土工格柵,接著鋪筑20cm厚中粗砂墊層,然后進行吹填砂路基的施工,最后采用粘土進行包邊和封頂。具體要求如下:
一、碎石墊層施工
軟基處理工程完成經(jīng)檢測合格后,在其上鋪30cm厚級配碎石墊層。
1. 準備工作:
(1) 鋪筑前,將路床所有浮土、雜物清除干凈,并嚴格整型和壓實使其符合設(shè)計圖紙要求。
(2) 路床表面上的車轍或松軟部分和壓實不足的地方以及任何不符合規(guī)定要求的表面都應翻松、清除或摻填同類材料重新進行整修碾壓。
(3) 施工前對路床進行復驗,同時保證臨時排水設(shè)施的完好。
(4) 恢復中線測量:直線段每20~25m設(shè)一樁,平曲線每10~15m設(shè)一樁。
2. 攤鋪:
(1) 分層平行攤鋪,每層鋪設(shè)的寬度,應超出路堤的設(shè)計寬度30cm,以保證修整路基邊坡后的路堤邊緣有足夠的壓實度。
(2) 采用重型振動壓路機碾壓時,一層壓實厚度不宜超過30cm。根據(jù)所配置的壓路機械,壓實總厚度超過一層壓實厚度時應分層攤鋪,但每層壓實厚度不得小于10cm。
(3) 攤鋪必須用經(jīng)監(jiān)理工程師批準的機械進行作業(yè),將集料按松鋪厚度均勻地攤鋪在規(guī)定的寬度上。
3. 拌和及整型:
(1) 級配碎石的最大粒徑不應超過31.5mm(方孔篩),壓碎值不應大于26%。碎石中不應含有粘土塊、植物等有害物質(zhì),針片狀顆?偤坎粦^20%。
(2) 拌和結(jié)束后,其含水量應稍高于最佳含水量,以彌補碾壓過程中的水分消耗。
在整型過程中,必須禁止任何車輛通行。 (轉(zhuǎn)下頁)
Cards on the table contents:
The project roadbed construction in soft ground after the completion of the first paving stone cushion 30cm thick, holes and a layer of geogrid 40 type two-way, and then paving 20cm thick in the sand cushion, and then fill sand subgrade construction, and finally carried out by wrapping the clay and capped. Specific requirements are as follows:
First, construction of gravel cushion
After completion of soft ground after passing inspection, be capped 30cm thick graded crushed stone bedding.
1. Preparation:
(1) paving before the road bed all the surface dust, debris cleared away, and strictly cosmetic and compaction to meet the design requirements of the drawings.
(2) Road bed surface rutting or soft parts and compaction deficiencies and does not meet the requirements of any surface should be turned loose, clear or mixed with similar material to re-fill repair RCC.
(3) pre-construction bed LO retesting, while ensuring the integrity of the temporary drainage facilities.
(4) restoration of midline measurement: 20 ~ 25m straight line set up one of each, every 10 ~ 15m horizontal curve set 1.
2. Paving:
(1) hierarchical parallel to paving, the width of each floor laying, should go beyond the design of embankment width 30cm, to ensure the repair of embankment after embankment slope edge of a sufficient degree of compaction.
(2) using heavy vibratory roller compacted, the compacted layer thickness of not more than 30cm. According to the mechanical configuration of the roller compaction the total thickness of the layer should be more than the thickness of a layer of compacted paving, but the thickness of each layer compacted not less than 10cm.
(3) paving must be approved by the supervising engineer for operations of machinery will be loose aggregate thickness being evenly by spreading the required width.
3. Mixing and integer:
(1) maximum size gravel gradation shall not exceed 31.5mm (square hole sieve), crushing the value should not exceed 26%. Stone blocks should not contain clay, plants and other harmful substances, the total content of flat-elongated particles should not exceed 20%.
(2) After mixing, the water content should be slightly higher than the optimum water content, to make up for the water consumption of rolling process.
In the integer, it is necessary to prohibit any vehicle traffic. (Next page)