交底內(nèi)容:
1、 本工程人行道按照路面結(jié)構(gòu)圖(圖號DL-6-02、DL-6-05、DL-6-06等)進行施工。
2、 人行道磚的顏色及鋪砌樣式應事先取得甲方單位的認可。
3、 人行道墊層采用6%水泥穩(wěn)定石屑厚15cm,人行道磚使用的材料是:水泥混凝土機壓彩色通透聯(lián)體磚,規(guī)格為25×12.5×5cm。
4、 測量放線:
利用側(cè)石為邊線,放出中線;并約隔5m左右測放水平樁,以控制方向及高程。桉標高及中、邊線縱橫掛線,以掛線為依據(jù)鋪砌。
5、 鋪砌人行道磚時,先鋪一層2cm厚的1:3水泥砂漿臥底層進行調(diào)平,再進行鋪砌預制塊彩磚。
預制塊鋪好后,用水泥砂漿填灌板縫,并用灰匙搗插板縫
Cards on the table contents:
1, the project in accordance with the road pavement structure (Figure No. DL-6-02, DL-6-05, DL-6-06, etc.) construction.
2, the color of brick sidewalks and paving patterns Party units should obtain prior approval.
3 cushion with 6% cement sidewalk stable thick stone chips 15cm, brick sidewalk materials used are: color translucent concrete compression machine conjoined brick, size 25 × 12.5 × 5cm.
4, measuring up line:
Use of side stone edges, release midline; and measured in cycles of approximately 5m placed around the level of piles, to control the direction and elevation. Eucalyptus elevation and in vertical and horizontal edges hang to hang-based paving.
5, when laying brick sidewalks, Xian Pu 2cm thick layer of 1:3 cement mortar undercover leveling layer, further preform color brick paving.
After the precast blocks laid out, filled with cement mortar filling seams, and seams with gray key trace interpolation